Financial functions follow one rule: money you pay out is negative, money you receive is positive. Use a rate per period and the number of periods in the same unit. For monthly payments on a yearly rate, divide the rate by 12 and multiply the years by 12.

FunctionSyntaxFinds
PMT=PMT(rate, nper, pv, [fv], [type])Regular payment (EMI)
PPMT / IPMT=PPMT(rate, per, nper, pv)Principal part / interest part of one payment
FV=FV(rate, nper, pmt, [pv], [type])Future value
PV=PV(rate, nper, pmt, [fv], [type])Present value
NPER=NPER(rate, pmt, pv, [fv], [type])Number of periods
RATE=RATE(nper, pmt, pv, [fv], [type])Interest rate per period
NPV=NPV(rate, value1, value2, ...)Net present value
IRR=IRR(values, [guess])Internal rate of return

type: 0 or omitted = payment at the end of the period; 1 = at the beginning.

Worked examples

SituationFormulaResult
EMI on a loan of ₹5,00,000 at 9% a year for 5 years=PMT(9%/12,60,500000)-10,379.18 a month (negative = you pay). Total paid = 10,379.18 × 60 = 6,22,750.66, so interest = ₹1,22,750.66.
SIP of ₹5,000 a month at 6% a year for 5 years=FV(6%/12,60,-5000)₹3,48,850.15
Same SIP, paid at the start of each month=FV(6%/12,60,-5000,0,1)₹3,50,594.40
₹1,00,000 lump sum at 8% for 5 years=FV(8%,5,0,-100000)₹1,46,932.81
Present value of ₹10,000 due in 3 years at 10%=PV(10%,3,0,-10000)₹7,513.15
Years to double money at 8%=NPER(8%,0,-1,2)about 9.01 years
Monthly rate behind the EMI above=RATE(60,-10379.18,500000)0.75% a month, so 9% a year

NPV and IRR

Cash flows for a project: -1,00,000 now, then +40,000, +50,000, +60,000 at the end of years 1, 2 and 3. Discount rate 10%.

  • =NPV(10%,40000,50000,60000)-100000 → ₹22,764.84. NPV assumes the first value comes at the END of period 1, so the initial investment is subtracted outside the function.
  • =IRR(A1:A4) with the four flows in A1:A4 (including -1,00,000) → 21.65%. IRR is the rate at which NPV becomes zero.
  • XNPV and XIRR do the same with actual dates; MIRR uses separate borrowing and reinvestment rates.

Depreciation

Asset cost ₹1,00,000, salvage value ₹10,000, life 5 years.

FunctionFormulaYear 1Method
SLN=SLN(100000,10000,5)18,000 every yearStraight-line: (cost - salvage) ÷ life
DB=DB(100000,10000,5,1)36,900Fixed declining balance
DDB=DDB(100000,10000,5,1)40,000 (year 2: 24,000)Double-declining balance, rate = 2 ÷ life
SYD=SYD(100000,10000,5,1)30,000Sum-of-years' digits

Other: =EFFECT(nominal_rate, npery) gives the effective annual rate; =NOMINAL(effect_rate, npery) does the reverse.