Power and Hydropower

Power and Hydropower

Energy and Infrastructure · 2 min read

J&K's rivers give the UT huge hydropower potential, but only about a quarter has been harnessed.

Potential and installed capacity

ItemFigure
Estimated potential18,000 MW
Identified potential14,867 MW
Harnessed3,540.15 MW (23.81%) in 31 projects
Central sector (NHPC)2,250 MW (6 projects)
State sector (JKPDC)1,197.40 MW (13 projects)
Private / IPP92.75 MW (12 projects)
Hydropower in J&K: installed and under construction (MW)Hydropower in J&K: installed and under construction (MW). Installed 3,540 MW (31 projects); four projects add 3,014 MWHydropower in J&K: installed and under construction (MW)Installed 3,540 MW (31 projects); four projects add 3,014 MWCentral sector (NHPC, 6)2,250State sector (JKPDC, 13)1,197.4Private / IPP (12)92.75Pakal Dul (building)1,000Ratle (building)850Kiru (building)624Kwar (building)540MWSource: Economic Survey 2025-26; NHPC and CVPPL project details as reported to Parliament | JKEdusphere
Installed and under-construction hydropower of J&K (MW).

Main operating projects

ProjectRiverMWDistrictOwner
BagliharChenab900RambanJKPDC (State)
SalalChenab690ReasiNHPC
Uri-IJhelum480BaramullaNHPC
DulhastiChenab390KishtwarNHPC
KishangangaKishanganga (Neelum)330BandiporaNHPC
Uri-IIJhelum240BaramullaNHPC
Sewa-IISewa120KathuaNHPC

Under construction (four projects, 3,014 MW)

ProjectMWCost (Rs crore)Target (as told to Parliament)
Pakal Dul (Marusudar)1,00012,728December 2026
Ratle (Chenab, Kishtwar)8505,282November 2028
Kiru (Chenab)6245,409December 2026
Kwar (Chenab)5404,526March 2028

Combined cost Rs 27,945 crore. The Economic Survey says generation capacity will be doubled by 2028. Sawalkot (1,856 MW) on the Chenab (NHPC) is planned; clearances are in progress.

Power distribution

  • Transmission and distribution capacity: 34,839 MVA, 1,76,601 circuit km, up 44% since 2020.
  • Consumers: about 24.59 lakh.
  • Per capita consumption: 1,488 kWh (from 1,171 kWh in nine years).
  • Smart meters: 11.71 lakh installed against about 21 lakh target; the Budget aims at 100% smart metering in urban areas by December 2026.

Keep practising

Notes are only half the work. Test yourself with questions and discuss doubts with other aspirants.

Prepared for exam revision from the J&K Economic Survey 2025-26, J&K Budget 2026-27, PRS Legislative Research, NITI Aayog and replies in Parliament and the Legislative Assembly. Figures are advance estimates or latest available and official replies sometimes differ, so check the latest Economic Survey and Budget before relying on them. Found a mistake? Tell us.